Before work can start on a renovation in a New York City co-op or condo, the building needs a complete set of documents, often called the board package or alteration package. An incomplete package is one of the most common reasons approvals take longer than expected. This checklist covers what boards and managing agents typically ask for. Every building has its own list, so always start from your building's alteration agreement.

From the owner

  • The signed alteration agreement, which sets the rules for the work and your responsibilities.
  • A written scope of work describing what will change in each room.
  • Deposits and review fees, such as a refundable damage deposit and fees for the building's architect or engineer.
  • Any required consents, for example from a neighbor if work affects a shared wall.

From the architect or engineer

  • Drawings showing existing and proposed layouts, plumbing and electrical changes, and details of wet areas and waterproofing.
  • DOB filings and permits for work that requires them, or a letter explaining why none are needed. See our article on when an NYC renovation needs a DOB permit.
  • Landmarks approval in landmarked buildings, where permitted work is also reviewed by the Landmarks Preservation Commission.

From the contractor

  • Insurance certificates for general liability, workers' compensation and disability, naming the building and managing agent as additional insureds, with the limits the building requires.
  • License information for the general contractor and for the licensed trades, such as the master plumber and electrician.
  • A construction schedule showing the start date, the phases and the expected completion.
  • Logistics, including working hours, deliveries, elevator use, protection of common areas and debris removal.

Testing in older buildings

Many projects need an asbestos assessment before permitted work, and buildings constructed before 1978 require lead-safe practices when painted surfaces are disturbed. Boards often ask to see the reports. Ordering them early prevents a hold-up just before work starts.

Review and approval

Once the package is complete, the managing agent passes it to the board and, often, the building's architect or engineer. Questions or requested changes are common; answering them quickly and completely keeps the review short. Some co-ops also limit major work to certain months, which affects when the package should be submitted.

During and after the work

Approval is not the end. Boards may inspect during construction, and at the end they usually want proof that permits are signed off and the work matches the approved plans before returning the deposit.

We prepare our part

Gurri Remodel is a licensed NYC remodeling contractor that has worked with co-op and condo boards across Manhattan and Brooklyn since 1997. We prepare the contractor side of the package, coordinate with your architect, and plan the schedule around the review. See our co-op and condo renovation services, read about condo renovation rules, or contact us.