Many New York City owners plan to renovate the kitchen now and the bathroom later. Often it makes more sense to do both at once. The approvals, the plumbing work and the disruption to the building are largely the same, and doing them together can save time and repeated paperwork. This article explains when combining them makes sense and how to plan the work.

Why combine them

  • One approval. Co-op and condo boards review renovations through an alteration agreement. One application covering both rooms is usually simpler than two separate ones a year apart.
  • One plumbing plan. Kitchens and bathrooms both connect to the building's risers. Planning both together means water shut-offs, riser work and permits can be coordinated once.
  • One disruption. Neighbors, the super and the managing agent deal with one project, one set of deliveries and one period of noise.
  • A consistent design. Stone, tile, millwork and fixtures can be chosen as a set, so the apartment feels finished as a whole.

What to check first

Before committing, confirm the building's rules on work hours, any seasonal restrictions on renovation, and whether moving either room is allowed. Many co-ops limit wet-over-dry layouts, which affects where a new bathroom or relocated kitchen can go. Our co-op vs. condo renovation guide covers how boards differ.

Sequencing the work

A combined project usually follows this order:

  1. Protection and demolition of both rooms, with common areas and elevators protected.
  2. Rough plumbing and electrical in both rooms while walls and floors are open, including any riser connections and inspections.
  3. Waterproofing in the bathroom, which needs time and testing before tile.
  4. Tile and stone in the bathroom, while kitchen cabinetry is installed.
  5. Countertop templating once kitchen cabinets are in, then fabrication and installation.
  6. Fixtures, appliances and finishes in both rooms, then final inspections and sign-offs.

Overlapping the trades this way is where much of the time saving comes from.

Living arrangements

With the kitchen and main bathroom both out of service, most owners move out for at least part of the work. If the apartment has a second bathroom, it can sometimes stay in use. We agree on this at the start, so the schedule reflects whether the apartment is occupied.

Budget and selections

Combining rooms does not reduce what each room costs to build, but it can reduce repeated costs such as protection, permits, filings and project management time. The bigger benefit is certainty: when tile, stone, cabinetry and fixtures for both rooms are selected before work starts, there are fewer delays waiting for decisions.

Planning a combined renovation

Gurri Remodel is a licensed NYC remodeling contractor that has renovated kitchens and bathrooms in Manhattan and Brooklyn apartments since 1997. We handle the contractor side of the board package, coordinate with your architect or designer, and run both rooms on one schedule. See our kitchen remodeling, bathroom remodeling and apartment renovation services, or contact us.

Leave A Comment

Your email address will not be published. Required fields are marked *